SmarteBuild
Running the job

Move one date and see what moves with it

A programme that does not understand dependencies is a list of dates that goes stale the first time it rains. SmarteBuild's schedule is six views over one set of tasks — so a change made in the Gantt shows up in the calendar, the call-up sheet and the cash flow at the same time.

Available on the Builder plan

app.smartebuild.com.au/schedule
The SmarteBuild schedule as a Gantt chart, with tasks, durations and dependency lines across the build programme.
Six views, one set of tasks

The same job, looked at six ways

They share the same underlying data, so a change in one appears in all of them. You are never reconciling a programme against a calendar against a call-up list.

Tasks

The list. Add, edit and check off work.

Schedule

The Gantt — durations, dependencies, the critical path.

Calendar

What is happening on which day.

Call up

Telling subcontractors when to come.

Bookings

Who has confirmed.

Cash flow

What the job costs, over time.

Which view answers which question

Planning a job
Start in Tasks to get the work down, then move to Schedule to give it durations and dependencies.
Running a week
Calendar and Call up. What is on this week, and who needs telling.
Is the subbie actually coming?
Bookings.
When will we be finished?
Schedule. The Gantt is the only view that can answer it, because it is the only one that understands dependencies.
When do we need the money?
Cash flow.

Do not try to plan in the calendar. It shows what is scheduled; it does not understand why. Move a task there and nothing downstream follows. Plan in the Schedule, where dependencies mean a change flows through the rest of the job.

app.smartebuild.com.au/callupsheet
The call-up view showing which trades are due to be called this week, based on each task's notice period.
Twenty minutes on a Monday, across every job.
Tasks are the unit

The more a task knows, the more the other views can do

Everything in the schedule is a task. A task with a name and nothing else appears in the list and does nothing anywhere else. A task that carries its cost centre, its supplier and its call-up period drives the call-up sheet, the bookings view and the cash flow projection without any further work.

  • A duration and dates
  • Predecessors, so it follows other work
  • A cost centre and a supplier, connecting it to the estimate
  • A cost, or a link to a purchase order
  • A call-up period, so the subcontractor is told in time

Call-up notice varies enormously

Set it per task, because trades are not alike:

Concrete1 week
Carpenter2 weeks
Roof tiler2 weeks
Cabinetmaker6 weeks — a manufacturing lead time
Windows8 weeks — ordered, not called up

Ask each of your regular subcontractors what notice they want, set it once, and the call-up view works out the rest.

Getting the first version down

Two ways to start, neither of them a blank page

The reason most builders programme one job in ten is the first hour, staring at an empty Gantt. Both of these get you to something worth editing in a couple of minutes.

Start from a template

Import Template loads a ready-made programme — tasks, durations and the links between them. Your own past jobs are there, and so are SmarteBuild's own residential programmes, so a new customer is not starting from nothing on day one.

Start from your own cost codes

Build from Cost Codes makes one task per cost code on the job, in order, each one following the last and carrying its own budget. Then you drag the durations to reality instead of typing the trade names in.

Both replace the current programme, so they are a starting point rather than something to run over a job you have already planned.

Long-lead items are orders, not call-ups

Cabinets and windows need ordering months ahead, not calling up a fortnight ahead. If a long-lead item only exists in your programme as a call-up, it is already late. Put the order date in the schedule as its own task.

A closer look at the schedule

Six views over one set of tasks — here are three of them.

The tasks list view with durations, cost centres and suppliers.
Tasks, and everything they carry
The calendar view showing what is happening on which day.
The week at a glance
Dependency lines between tasks on the Gantt.
Dependencies, drawn

What it connects to

Nothing in SmarteBuild is an island — that is the point of it. Schedule & Gantt reads from and feeds into these.

  • Call-Up Sheets

    The week ahead on one page, so no trade gets forgotten

  • Cash Flow

    What the job costs you and when, projected across the programme

  • Purchase Orders

    Raise orders straight from the BOQ and send them without re-keying

  • Projects & Costings

    Contract stages, markups and the numbers behind every job

Want the detail?

The help centre documents Schedule & Gantt step by step, with worked examples — written for people using it, not for a brochure.

Start with one job and see

Try the whole thing free for 30 days. No credit card to start, and no lock-in contract.